As part of this project 6000 semi loads or 74,000 cubic yards of dirt was imported to the site. Additionally, 59 loads or 1500 tons of bedding, rock and class 1 structural fill we brought to the site. Close coordination with the project manager, owner and the Town of Parker was needed to make this project a success. The Fiore Logistic team rose to the occasion and delivered for the team.